Summary:
Metro’s contractor, Walsh-Shea Corridor Constructors (WSCC) will be working on the installation of temporary supports or falsework for a new bridge over La Cienega Bl and the 405 freeway on Florence Av between Glasgow Av and Ash Av.
Essentials:
WHAT: Falsework Installation
WHEN: Beginning September 26, 2016 from 8:30am to 3:30pm and 9pm to 5am, Monday throughFriday, weather permitting.
WHERE: Florence Av between Glasgow Av and Ash Av.
DURATION: Eight months
What to Expect:
Access for emergency responders will be maintained.
One westbound lane on Florence Av will be reduced during the day.
There will be two lane reductions on Florence Av during the night activity, with one lane maintained in each direction.