AM Daily Construction Traffic Update: 3/8/16

03/8/16

AM Daily Traffic Impacts

Tuesday, March 8, 2016 

Hyde Park Station: Pile installation on Crenshaw Blvd. will require closure of the northbound and southbound No. 1 lanes and left turn lanes at 60th St. from 9 a.m. to 2:30 p.m. 

Downtown Inglewood Station: Drilling work on Florence Ave. will require the closure of the westbound No. 2 lane at Locust St. from 9 a.m. to 2:30 p.m. 

Aviation/Century Station: Work on a support wall on Metro right-of-way along Aviation Blvd. will affect southbound traffic with interruption to the No. 2 lane from 111th St. to Imperial Hwy. from 9 a.m. to 2 p.m.

Downtown Inglewood Station: The guideway closure at Cable St. requires a full northbound and southbound closure of Cable St. at Ivy Ave. until October 15, 2016. 

Westchester/Veterans Station: The grade closure at Portal Ave. requires a full eastbound and westbound closure of Portal Ave. at the Bellanca Ave. alleyway until May 2, 2016.

Read more
Add your reaction Share

STREET CLOSURE: 111th St. & Aviation Blvd

Street Closure at 111th St. and Aviation Blvd: MARCH 14, 2016

 

Summary

Walsh-Shea Corridor Constructors (WSCC) will be implementing a full street closure of 111th St. at Aviation Blvd. for two weeks. The closure is necessary for the installation of temporary supports (falsework) for a new bridge over 111th St.

Essentials

WHAT: Street closure for falsework installation

WHEN: March 14, 2016 through March 25, 2016 from 9 p.m. to 6 a.m., Monday through Friday, weather permitting.

WHERE: 111th St. at Aviation Blvd.

DURATION: Two weeks

What to Expect

> Local access into the Imperial Cargo Complex will be maintained at Imperial Hwy. and Douglas St.

> Access through 111th St. will be restricted.

> Pedestrian access will be maintained on the west side of Avaiation, south of 111th St.

Read more
Add your reaction Share

AM Daily Construction Traffic Update: 3/7/16

03/7/16

Daily Traffic Impacts

Monday, March 7, 2016 

Downtown Inglewood Station: The guideway closure at Cable St. requires a full northbound and southbound closure of Cable St. at Ivy Ave. until October 15, 2016. 

Westchester/Veterans Station: The grade closure at Portal Ave. requires a full eastbound and westbound closure of Portal Ave. at the Bellanca Ave. alleyway until May 2, 2016.

Read more
Add your reaction Share

AM Daily Construction Traffic Update: 3/3/16

03/3/16

AM Daily Traffic Impacts

Thursday, March 3, 2016 

Leimert Park Station: Pile installation on Crenshaw Blvd. will require closure of the northbound and southbound No. 1 lanes and left turn lanes from 9 a.m. to 2:30 p.m. 

Martin Luther King Jr. Station: Jet grouting on Crenshaw Blvd. will require closure of the northbound and southbound No. 1 lanes between MLK Blvd. and 39th St. from 9 a.m. to 2:30 p.m. 

Aviation/Century Station: Work on a support wall on Metro right-of-way along Aviation Blvd. will affect southbound traffic with interruption to the No. 2 lane from 111th St. to Imperial Hwy. from 9 a.m. to 2 p.m.

Aviation/Century Station: Excavation along the Metro right-of-way on Aviation Blvd. will affect southbound traffic with interruption to the No. 1 and No. 2 lanes from 104th St. to 111th St. to between 9 a.m. to 2 p.m.

Downtown Inglewood Station: The guideway closure at Cable St. requires a full northbound and southbound closure of Cable St. at Ivy Ave. until October 15, 2016. 

Westchester/Veterans Station: The grade closure at Portal Ave. requires a full eastbound and westbound closure of Portal Ave. at the Bellanca Ave. alleyway until May 2, 2016.

Read more
Add your reaction Share

PM Daily Construction Traffic Update: 3/2/16

03/2/16

Daily Traffic Impacts

Wednesday, March 2, 2016 

Leimert Park Station: Jet grouting on Crenshaw Blvd.  will require closure of the northbound and southbound No. 1 lanes between MLK Blvd. and 39th St. from 9 p.m. to 6 a.m. 

Martin Luther King Jr. Station: An equipment move on Crenshaw Blvd. will require a closure of the northbound No. 1 lane and left turn lane at Vernon Ave. from 9 p.m. to 6 a.m.

Martin Luther King Jr. Station: Soil treatment work on Crenshaw Blvd. will require a full closure between MLK Blvd. and Stocker St. from 9 p.m. to 6 a.m.

Downtown Inglewood Station: The guideway closure at Cable St. requires a full northbound and southbound closure of Cable St. at Ivy Ave. until October 15, 2016. 

Westchester/Veterans Station: The grade closure at Portal Ave. requires a full eastbound and westbound closure of Portal Ave. at the Bellanca Ave. alleyway until May 2, 2016.

Read more
Add your reaction Share

AM Daily Construction Traffic Update: 3/2/16

03/2/16

AM Daily Traffic Impacts

Wednesday, March 2, 2016 

Leimert Park Station: Pile installation on Crenshaw Blvd.will require closure of the northbound and southbound No. 1 lanes and left turn lanes from 9 a.m. to 2:30 p.m. 

Martin Luther King Jr. Station: Jet grouting on Crenshaw Blvd. will require closure of the northbound and southbound No. 1 lanes between MLK Blvd. and 39th St. from 9 a.m. to 2:30 p.m. 

Aviation/Century Station: Work on a support wall on Metro right-of-way along Aviation Blvd. will affect southbound traffic with interruption to the No. 2 lane from 111th St. to Imperial Hwy. from 9 a.m. to 2 p.m.

Aviation/Century Station: Excavation along the Metro right-of-way on Aviation Blvd. will affect southbound traffic with interruption to the No. 1 and No. 2 lanes from 104th St. to 111th St. to between 9 a.m. to 2 p.m.

Downtown Inglewood Station: The guideway closure at Cable St. requires a full northbound and southbound closure of Cable St. at Ivy Ave. until October 15, 2016. 

Westchester/Veterans Station: The grade closure at Portal Ave. requires a full eastbound and westbound closure of Portal Ave. at the Bellanca Ave. alleyway until May 2, 2016.

Read more
Add your reaction Share

Daily Construction Traffic Update: 3/1/16

03/1/16

Daily Traffic Impacts

Tuesday, March 1, 2016 

Martin Luther King Jr. Station: Soil treatment work on Crenshaw Blvd. will require a full closure between MLK Blvd. and Stocker St. from 9 p.m. to 6 a.m.

Leimert Park Station: Jet grouting on Crenshaw Blvd. between MLK Blvd. and 39th St. will require closure of the northbound and southbound No. 1 lanes from 9 p.m. to 6 a.m. 

Downtown Inglewood Station: The guideway closure at Cable St. requires a full northbound and southbound closure of Cable St. at Ivy Ave. until October 15, 2016. 

Westchester/Veterans Station: The grade closure at Portal Ave. requires a full eastbound and westbound closure of Portal Ave. at the Bellanca Ave. alleyway until May 2, 2016.

Read more
Add your reaction Share

Daily Construction Traffic Update: 2/23/16

02/23/16

Daily Traffic Impacts

Tuesday, February 23, 2016

Hyde Park Station

Utility Repair work will affect traffic on Crenshaw Blvd. with an interruption to the No. 1 lane and left turn lane both northbound and southbound at Hyde Park Blvd. between 9 a.m. and 2:30 p.m.

Hyde Park Station

Tree Removal on Crenshaw Blvd. will affect southbound traffic with interruption to the No. 2 lane at 60th St. between 9 a.m. and 3 p.m.

Aviation/Century Station:

Work on a support wall on Metro right-of-way along Aviation Blvd. will affect southbound traffic with interruption No. 2 lane from Imperial Highway to 111th St. between 9 a.m. and 2 p.m.

Aviation/Century Station:

Excavation work on Metro right-of-way along Aviation Bl will affect southbound traffic with interruption No. 1 and No. 2 lane from 104th St to 111th St. between 9 a.m. and 2 p.m. 

Long Term Closures

Downtown Inglewood Station:
Guide-way closure of Cable Pl. will impact northbound and southbound traffic with a Full Closure at Ivy Ave. Ongoing until 10/15/16.

Westchester/Veterans Station:
At-grade crossing at Portal Ave. will affect eastbound and westbound traffic with aFull Closure at the alley to Bellanca Ave. Ongoing until 5/2/16.

Read more